Algonquin Gas Transmission, LLC Submits Monthly Progress Report for Cape Cod Canal Pipeline Relocation Project
Algonquin Gas Transmission, LLC has submitted its eighth monthly progress report to the Federal Energy Regulatory Commission (FERC) for the Cape Cod Canal Pipeline Relocation Project, which aims to relocate a pipeline under the Cape Cod Canal in Massachusetts. The project, approved by FERC in January 2025, is currently in the pre-filing review process. As of August 2025, Algonquin has secured survey permission on 97.62% of the proposed project right-of-way tracts and has completed 88% of the civil survey. The company has also filed draft resource reports and an environmental assessment with FERC, and is awaiting comments from regulatory agencies.
Key Takeaways:
- Algonquin Gas Transmission, LLC has secured survey permission on 97.62% of the proposed project right-of-way tracts.
- The civil survey for the project is 88% complete.
- Draft resource reports 1 and 10 were filed with FERC on February 5, 2025, and draft resource reports 1 through 12 were filed on June 16, 2025.
- Algonquin has filed a draft applicant prepared environmental assessment with FERC on August 22, 2025.
- The project is currently in the pre-filing review process, with FERC approval granted in January 2025.
- Algonquin is anticipating comments from regulatory agencies on the environmental assessment in mid-September 2025.
- The final application is expected to be submitted in late September 2025.
Statistics:
- 97.62% of proposed project right-of-way tracts have been granted survey permission.
- 88% of the civil survey is complete.
- 12 draft resource reports have been filed with FERC, with comments received from regulatory agencies on July 17 and July 18, 2025.
- 1 draft applicant prepared environmental assessment has been filed with FERC, with comments anticipated in mid-September 2025.
- The project is expected to submit its final application in late September 2025.
Sources:
- Algonquin Gas Transmission, LLC, "Algonquin Gas Transmission, LLC Cape Cod Canal Pipeline Relocation Project Docket No. PF25-4-000 FERC Pre-Filing Process Monthly Progress Report Period Ending: August 31, 2025 Report #: 8"
- Federal Energy Regulatory Commission (FERC), "Algonquin Gas Transmission, LLC Cape Cod Canal Pipeline Relocation Project Docket No. PF25-4-000"
- 18 C.F.R. SS 157.21(f)(6) (2024).