Anderson Dam Seismic Retrofit Project Construction Progress Report for September 2025

The Santa Clara Valley Water District has submitted a construction progress report for the Anderson Dam Seismic Retrofit Project to the Federal Energy Regulatory Commission. The report covers activities that occurred during September 2025, as required by both FERC's Anderson Dam Tunnel Project - Phase 1 Construction Authorization (April 09, 2021) and the ADTP Quality Control Inspection Program (QCIP) Version 7 (September 17, 2024). The report highlights key milestones and progress made during the month.

Key Takeaways:

  • The report is submitted to fulfill two requirements: FERC's Anderson Dam Tunnel Project - Phase 1 Construction Authorization (April 09, 2021) and the ADTP Quality Control Inspection Program (QCIP) Version 7 (September 17, 2024).
  • The report covers activities that occurred during September 2025, including progress made in the Anderson Dam Tunnel Project.
  • The ADTP Quality Control Inspection Program (QCIP) Version 7 stipulates that Valley Water file monthly Construction Progress Reports.
  • The report includes a list of recipients, including Christopher Dorsey, P.E., Supervising Engineer, and Austin Roundtree, P.E., Area Engineer, DSOD Area 5.
  • The report is electronically signed using Docusign Envelope ID: 4940FF0C-71A5-4685-9396-00C477F59925.

Statistics:

  • The report is submitted on October 15, 2025.
  • The Anderson Dam Tunnel Project was authorized by FERC on April 09, 2021.
  • The ADTP Quality Control Inspection Program (QCIP) Version 7 was released on September 17, 2024.
  • The report is CC'd to the Federal Energy Regulatory Commission, ferconline.ferc.gov/eFiling.aspx.
  • The complete document can be viewed at this link: https://elibrary.ferc.gov.

Sources:

  • Anderson Dam Tunnel Project - Phase 1 Construction Authorization (FERC, April 09, 2021)
  • ADTP Quality Control Inspection Program (QCIP) Version 7 (September 17, 2024)
  • https://elibrary.ferc.gov
  • FERC's Anderson Dam Tunnel Project - Phase 1 Construction Authorization (April 09, 2021)