Anderson Dam Seismic Retrofit Project Construction Progress Report

The Anderson Dam Seismic Retrofit Project, under the management of Santa Clara Valley Water District, has submitted a monthly construction progress report to the Federal Energy Regulatory Commission (FERC) for July 2025. The report covers the ongoing construction efforts and progress made during the specified month. The submission of this report fulfills two requirements: the FERC's Anderson Dam Tunnel Project - Phase 1 Construction Authorization (April 09, 2021) and the ADTP Quality Control Inspection Program (QCIP) Version 7 (September 17, 2024).

Key Takeaways:

  • The report is submitted to meet the requirements of FERC's Anderson Dam Tunnel Project - Phase 1 Construction Authorization, which stipulates the submission of monthly Construction Progress Reports.
  • The ADTP Quality Control Inspection Program (QCIP) Version 7 also requires the submission of monthly Construction Progress Reports, which is fulfilled by this document.
  • The report is signed electronically using Docusign, with an Envelope ID of F215A019-576E-4AFD-A868-FB026ACB0309.
  • The document has been cc'd to several entities, including the Federal Energy Regulatory Commission, the Division of Safety of Dams, and a board of consultants comprising experts in geotechnical engineering, seismology, and construction management.
  • The report covers the Anderson Dam Tunnel Project, FERC No. 5737, for the month of July 2025.
  • The document is available for viewing on the FERC eLibrary at https://elibrary.ferc.gov.

Statistics:

  • The report is submitted on August 14, 2025.
  • The document is electronically signed using Docusign.
  • The Envelope ID for the signed document is F215A019-576E-4AFD-A868-FB026ACB0309.
  • The report is cc'd to 15 entities, including Federal Energy Regulatory Commission, Division of Safety of Dams, and a board of consultants.

Sources:

  • Anderson Dam Seismic Retrofit Project Santa Clara Valley Water District 5750 Almaden Expressway, San Jose, CA 95118-3686 Valley Water Transmittal 1
  • FERC's Anderson Dam Tunnel Project - Phase 1 Construction Authorization (April 09, 2021)
  • ADTP Quality Control Inspection Program (QCIP) Version 7 (September 17, 2024)