ANR Pipeline Company Submits Supplemental Information to Federal Energy Regulatory Commission
The ANR Pipeline Company, a natural gas pipeline operator, has submitted supplemental information to the Federal Energy Regulatory Commission (FERC) regarding the placement into service of the South Wausau Meter Station facilities. The supplementary filing is in response to a previous request made on August 5, 2025, and provides clarification on the mechanical completion of the facilities. The submission also includes photos demonstrating the satisfactory rehabilitation and restoration of areas affected by the facilities.
Key Takeaways:
- ANR Pipeline Company submitted a request to FERC on August 5, 2025, to place into service the South Wausau Meter Station facilities, with an in-service date of August 15, 2025.
- ANR clarifies that mechanical completion of the South Wausau Meter Station facilities was achieved on August 15, 2025.
- The supplementary filing provides photos that demonstrate satisfactory rehabilitation and restoration of areas affected by the facilities.
- The submission is made in accordance with FERC's Order No. 703 and the e-filing guidelines.
- The document includes a photo log as an attachment, with a total of two pages and a single document content.
Statistics:
- Date submitted to FERC: August 18, 2025
- Document Accession Number: 20250818-5062
- Filed Date: August 18, 2025
- Number of Document Content(s): 1
- Document Size: 2 pages
Sources:
- ANR Pipeline Company, Docket No. CP23-15-000, "Wisconsin Reliability Project," August 18, 2025.
- Federal Energy Regulatory Commission, "Order Issuing Certificate and Approving Abandonment," Docket No. CP23-15-000, December 19, 2023.
- Federal Register, "Filing Via the Internet," Docket No. RM07-16-000, November 15, 2007.