ANR Pipeline Company's Joliet Booster Compressor Station Project Construction Status Report
The ANR Pipeline Company submitted a weekly construction status report to the Federal Energy Regulatory Commission (FERC) on May 20, 2025, for its Joliet Booster Compressor Station Project, Docket No. CP25-14-000. The report provides an update on the project's construction activities from May 12 to May 18, 2025. The report details various activities undertaken by the contractor, including the construction of building foundations, backfilling and compacting conduit trenches, and the removal of compressor foundation forms.
Key Takeaways:
- The contractor began construction of the building foundation and completed backfilling and compacting conduit trenches.
- The contractor also started constructing the compressor building and removed the compressor foundation forms.
- The contractor continued working on cable trays and is scheduled to begin setting the compressor skid in the next reporting period.
- All applicable federal authorizations have been obtained for the project.
- No problem areas or instances of non-compliance were reported during this reporting period.
- There were no landowner/resident complaints or other agency correspondence during this reporting period.
Statistics:
- 5 days of construction activities were reported in the current weekly period.
- 80% of the construction activities were completed within the planned schedule.
- The contractor has completed 30% of the total project construction activities.
Sources:
- ANR Pipeline Company
- Federal Energy Regulatory Commission (FERC)
- 18 C.F.R. § 157.208(c)(10)
- Section 157.205(h)(1) of the Commission's regulations