ANR Pipeline Company's Joliet Booster Compressor Station Project: Weekly Construction Status Report

The ANR Pipeline Company has submitted a weekly construction status report for its Joliet Booster Compressor Station Project to the Federal Energy Regulatory Commission. The report, dated July 30, 2025, provides an update on the project's construction activities, federal authorizations, and environmental compliance. The project, authorized on January 14, 2025, is proceeding with the construction of a compressor building, compressor skid, and piping system.

Key Takeaways:

  • The contractor continued construction of the compressor building, compressor skid, and accessories during the reporting period (July 21-27, 2025).
  • The contractor mobilized a frac tank to the site for a hydrostatic pressure test and assembled piping inside the facility.
  • No problem areas or instances of non-compliance were reported during this reporting period.
  • No landowner/resident complaints or other agency correspondence occurred during this reporting period.
  • The contractor plans to complete the compressor building, assemble the compressor skid, and begin restoration of the grade and topsoil during the next reporting period (July 28 - August 3, 2025).

Statistics:

  • Reporting period: July 21-27, 2025
  • Authorized start date: January 14, 2025
  • Project workspace: No waterbodies occur within the Project workspace.
  • Photos: 7 photos showcasing various aspects of the project, including a frac tank, compressor building, and cable tray supports.

Sources:

  • ANR Pipeline Company. (2025, July 30). Joliet Booster Compressor Station Project Docket No. CP25-14-000 Construction Status Report No. 19.
  • Federal Energy Regulatory Commission. (2025, January 14). Prior Notice Filing for Joliet Booster Compressor Station Project.