East Tennessee Natural Gas, LLC Submits Revised Compliance Filing to Federal Energy Regulatory Commission
The Federal Energy Regulatory Commission (FERC) has received a revised compliance filing from East Tennessee Natural Gas, LLC (East Tennessee). The filing, submitted on June 19, 2025, amends the company's tariff record to reflect rate decreases applicable to service on the Jewell Ridge Lateral, which were accepted without suspension, effective June 1, 2025. This filing comes after an administrative issue arose from East Tennessee's previous submission of rate decreases separately.
Key Takeaways:
- East Tennessee submitted the revised compliance filing to address an administrative issue resulting from the company's previous submission of rate decreases separately.
- The filing amends the company's tariff record to reflect rate decreases applicable to service on the Jewell Ridge Lateral, effective June 1, 2025.
- The revised tariff record, Version 21.1.0, will remain in effect until East Tennessee moves to place the previously filed tariff record (Version 22.0.0) into effect on November 1, 2025.
- East Tennessee requests that the Commission deem the previous tariff record moot and accept the revised compliance filing, effective June 1, 2025.
- A list of tariff records is provided, including the version number for the revised tariff record, effective June 1, 2025.
- The company has attached materials to the filing, including a marked (redlined) version of the tariff record being superseded and a certificate of service certifying that all materials have been served on affected customers.
Statistics:
- The revised tariff record, Version 21.1.0, is effective as of June 1, 2025.
- The revised tariff record will remain in effect until November 1, 2025.
- The original tariff record (Version 22.0.0) is estimated to be effective on November 1, 2025.
- Affected customers have been served on all materials listed in the "List of Materials Enclosed" section of the filing.
Sources:
- East Tennessee Natural Gas, LLC. (2025). Revised Compliance Filing. June 19, 2025.
- Federal Energy Regulatory Commission. (2025). Order Accepting and Suspending Tariff Records, Subject to Refund, and Establishing Hearing Procedures. Docket No. RP25-844-000. May 29, 2025.
- Electronic Tariff Filings, Order No. 714, III FERC Stats. & Regs., Regs. Preambles P 31,276 (2008), order establishing procedures, 130 FERC P 61,047, order establishing baseline filing schedule, 130 FERC P 61,228 (2010), final rule, Order No. 714-A, III FERC Stats. & Regs. P 31,356 (2014).