ES Sunlogy Bhd to Develop 155MWp Solar Power Plant in Sarawak for RM488.18mil

ES Sunlogy Bhd, a mechanical and electrical engineering services company, is set to develop a large-scale solar photovoltaic power plant in Long Lama, Baram, Sarawak, in partnership with Planet QEOS Sdn Bhd. The project, which will have a capacity of 155MWp, is expected to be funded through a combination of bank borrowings and internally generated funds, with a proposed ratio of 80:20. The company is currently in discussions with two banking institutions to secure the necessary financing facilities for the investment in the joint venture.

Key Takeaways:

  • The 155MWp solar power plant will be developed in Long Lama, Baram, Sarawak, at a cost of RM488.18mil.
  • The project will be funded through a combination of bank borrowings and internally generated funds, with a proposed ratio of 80:20.
  • ES Sunlogy Bhd is currently in discussions with two banking institutions to secure the necessary financing facilities for the investment in the joint venture.
  • The pre-development period for the project is estimated to be not later than 18 months from the date of the agreement.
  • Project commencement is expected to take place following the pre-development phase, with targeted completion no later than the end of 2027.
  • In the event of a funding shortfall or where additional cash equity is required beyond bank loans for the project, ES Sunlogy Bhd intends to meet such funding requirements via equity fundings.
  • The company plans to issue new shares to interested investors, subject to prevailing market conditions and approvals from Bursa Securities, shareholders, and relevant authorities, through a private placement exercise of up to 30% of its enlarged share capital.
  • The definitive joint venture agreement is expected to be negotiated and executed within the 18-month pre-development period.

Statistics:

  • Total project cost: RM488.18mil
  • Proposed funding ratio: 80:20 (bank borrowings:internally generated funds)
  • Pre-development period: not later than 18 months
  • Targeted completion date: no later than the end of 2027
  • Private placement exercise: up to 30% of enlarged share capital