Federal Energy Regulatory Commission Accepts Filing for Cancellation of Interconnection Service Agreement
The Federal Energy Regulatory Commission has accepted a filing by PJM Interconnection, L.L.C. (PJM) to cancel an interconnection service agreement and interconnection construction agreement among PJM, Payton Solar, LLC, and Commonwealth Edison Company. The filing was accepted effective August 1, 2025, after no protests or adverse comments were filed. This decision does not constitute approval of any service, rate, charge, or classification provided for in the filed document(s) and is without prejudice to any findings or orders that have been or may be made by the Commission in any proceeding now pending or hereafter instituted.
Key Takeaways:
- The Federal Energy Regulatory Commission has accepted a filing by PJM Interconnection, L.L.C. (PJM) to cancel an interconnection service agreement and interconnection construction agreement among PJM, Payton Solar, LLC, and Commonwealth Edison Company.
- The filing was accepted effective August 1, 2025, after no protests or adverse comments were filed in response to the public notice.
- The Commission's decision does not constitute approval of any service, rate, charge, or classification provided for in the filed document(s).
- The PJM Interconnection, L.L.C. submitted the notice of cancellation on July 1, 2025.
- The filing was granted under 18 C.F.R. § 375.307, with 18 C.F.R. § 385.214 providing for notices of intervention and motions to intervene.
- The Commission's order constitutes final agency action, and requests for rehearing may be filed within 30 days of the date of issuance.
Statistics:
- August 1, 2025: Effective date of the filing acceptance
- July 1, 2025: Date of submission of notice of cancellation by PJM
- The filing was granted under authority delegated to the Director, Division of Electric Power Regulation - East under 18 C.F.R. § 375.307
- 18 C.F.R. § 385.214 provides for notices of intervention and motions to intervene
- 30 days: Time period for filing requests for rehearing
Sources:
- PJM Interconnection, L.L.C., PJM Service Agreements Tariff, PJM SA No. 6917, PJM SA No. 6917 among PJM, Payton Solar and ComEd (1.0.0)
- 18 C.F.R. § 35.11
- Cent. Hudson Gas & Elec. Corp., 60 FERC P 61,106, reh'g denied, 61 FERC P 61,089 (1992)
- Sunflower Elec. Power Corp., 173 FERC P 61,054 (2020) (Danly, Comm'r, dissenting)