Federal Energy Regulatory Commission Accepts Generation Interconnection Agreement
The Federal Energy Regulatory Commission (FERC) has accepted the Generation Interconnection Agreement (GIA) among PJM Interconnection, L.L.C., Lillie Solar, LLC, and Virginia Electric and Power Company. The agreement was submitted on May 12, 2025, and was accepted for filing effective April 11, 2025. The filing was publicly noticed, and no protests or adverse comments were filed.
Key Takeaways:
- The FERC has accepted the GIA, effective April 11, 2025, as submitted by PJM Interconnection, L.L.C. on May 12, 2025.
- The GIA is among PJM as Transmission Provider, Lillie Solar, LLC as Project Developer, and Virginia Electric and Power Company as Transmission Owner.
- The agreement is designated as Original Service Agreement No. 7669 and was publicly noticed.
- No protests or adverse comments were filed in response to the submission.
- Pursuant to Rule 214 of the Commission's regulations, notices of intervention, timely-filed motions to intervene, and unopposed motions to intervene out-of-time filed before the issuance date of this order are granted.
- This action does not constitute approval of any service, rate, charge, classification, or any rule, regulation, contract, or practice affecting such rate or service provided for in the filed document(s).
- The order constitutes final agency action, and requests for rehearing by the Commission may be filed within 30 days of the date of issuance.
Statistics:
- Number of days between submission and acceptance: 29 days (May 12, 2025 to June 10, 2025)
- Number of filings: 1 (Generation Interconnection Agreement, ER25-2203-000)
- Number of days for filing to become effective: 18 days between filing (May 12, 2025) and effective date (April 11, 2025)
Sources:
- PJM Interconnection, L.L.C., PJM Service Agreements Tariff, PJM SA No. 7669
- FERC Order, Issued: July 10, 2025, Document Accession #: 20250710-3067