Federal Energy Regulatory Commission Approves Extension for Black River Dam Repair
The Federal Energy Regulatory Commission has approved a time extension for the repair of concrete degradation on the buttresses along the downstream side of the right forebay wall of the Black River Project (P-2569-NY). The owner, Erie Boulevard Hydropower, L.P., had requested an extension until December 31, 2024, to complete the repairs. The commission's review of the 2022 Dam Safety Surveillance and Monitoring Report found the submission to be acceptable and approved the extension of time request.
Key Takeaways:
- The Federal Energy Regulatory Commission has approved a time extension for the repair of concrete degradation on the Black River Project (P-2569-NY) until December 31, 2024.
- The commission's review of the 2022 Dam Safety Surveillance and Monitoring Report found the submission to be acceptable.
- The owner, Erie Boulevard Hydropower, L.P., had requested an extension to complete the repairs.
- The commission's Regional Engineer, John Spain, P.E., approved the extension of time request.
- The project is one of several developments in the Black River system, including the Herrings, Deferiet, Kamargo, and Sewalls Island developments.
- The approved extension is a result of ongoing efforts to ensure the safe operation and maintenance of the Black River Project.
Statistics:
- The concrete degradation on the buttresses along the downstream side of the right forebay wall is a concern for the safety of the Black River Project.
- The commission's review of the 2022 DSSMR indicates that the owner is taking steps to address the issue.
- The project has a complex history, with multiple developments in the Black River system.
- The commission's approval of the extension of time request highlights the importance of maintaining a safe and reliable hydroelectric infrastructure.
Sources:
- Federal Energy Regulatory Commission DELEGATED ORDER (Aug 10, 2023)
- Microsoft Outlook email from John Spain, P.E. to Mike Smith, Compliance Specialist (Aug 10, 2023)
- 2022 DSSMR for the Black River Project (P-2569-NY)