Federal Energy Regulatory Commission Approves New Non-Conforming Negotiated Rate Transportation Service Agreements
On October 25, 2022, the Federal Energy Regulatory Commission (FERC) issued a delegated order approving four new non-conforming negotiated rate transportation service agreements between El Paso Natural Gas Company and The Public Service Company of New Mexico. The agreements, which were filed by El Paso on September 27, 2022, will take effect on November 1, 2022. According to the order, no protests or adverse comments were filed in response to the application.
Key Takeaways:
- The FERC approved four new non-conforming negotiated rate transportation service agreements between El Paso Natural Gas Company and The Public Service Company of New Mexico.
- The agreements were filed by El Paso on September 27, 2022, and will take effect on November 1, 2022.
- The FERC's order notes that no protests or adverse comments were filed in response to the application.
- The Commission's Director, Marsha K. Palazzi, issued the delegated order on October 25, 2022.
- The agreements were filed under Docket No. RP22-1250-000, and the filing was publicly noticed.
- The FERC's actions in this matter do not constitute approval of the referenced filing or any rate, charge, classification, or any rule, regulation, or practice affecting such rate or service contained in the applicant's tariff.
- Requests for rehearing by the Commission may be filed within 30 days of the date of issuance of this order.
Statistics:
- 4 new non-conforming negotiated rate transportation service agreements were approved by the FERC.
- The agreements were filed by El Paso Natural Gas Company on September 27, 2022.
- The agreements will take effect on November 1, 2022.
- 30 days: the timeframe for requests for rehearing by the Commission to be filed.
Sources:
- Docket No. RP22-1250-000, Federal Energy Regulatory Commission, October 25, 2022.
- 18 C.F.R. P 375.307, Federal Energy Regulatory Commission regulations.