Federal Energy Regulatory Commission Approves Revisions to Interconnection Procedures

The Federal Energy Regulatory Commission has issued a delegated order approving revisions to the interconnection procedures submitted by Cube Yadkin Transmission LLC. The revisions were made in compliance with directives from a previous Commission order and the requirements of Order Nos. 2023 and 2023-A. The submittal was publicly noticed, and no protests or adverse comments were filed.

Key Takeaways:

  • The Commission has approved the revised Large Generator Interconnection Procedures, pro forma Large Generator Interconnection Agreement, Small Generator Interconnection Procedures, and pro forma Small Generator Interconnection Agreement submitted by Cube Yadkin Transmission LLC.
  • The revisions were made in compliance with the directives in a April 17, 2025 Commission order and the requirements of Order Nos. 2023 and 2023-A.
  • The filing was publicly noticed, and no protests or adverse comments were filed.
  • The order grants notices of intervention, timely-filed motions to intervene, and unopposed motions to intervene out-of-time filed before the issuance date of this order.
  • This action does not constitute approval of any service, rate, charge, classification, or any rule, regulation, contract, or practice affecting such rate or service provided for in the filed documents.
  • The revisions will take effect as requested, effective August 11, 2024.
  • The Commission has issued a final agency action order, and requests for rehearing may be filed within 30 days of the date of issuance of this order.

Statistics:

  • 1 document was submitted by Cube Yadkin Transmission LLC for filing (ER24-2517-001 DLO.docx).
  • The filing was made on June 16, 2025, and was publicly noticed.
  • No protests or adverse comments were filed.

Sources:

  • FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, DC 20426. (2025, September 24). Cube Yadkin Transmission LLC; Delegated Order. ER24-2517-001.
  • FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, DC 20426. (2025, April 17). Commission Order.
  • Improvements to Generator Interconnection Procs. & Agreements, Order No. 2023, 184 FERC P 61,054, order on reh'g, 185 FERC P 61,063 (2023), order on reh'g, Order No. 2023-A, 186 FERC P 61,199, errata notice, 188 FERC P 61,134 (2024).
  • Order Nos. 2023 and 2023-A, Improvements to Generator Interconnection Procs. & Agreements.