Federal Energy Regulatory Commission Issues Delegated Order for Arizona Public Service Company

The Federal Energy Regulatory Commission has issued a delegated order for the Arizona Public Service Company, accepting the Engineering & Procurement Agreement (Agreement) submitted on June 11, 2025. The Agreement was between the Arizona Public Service Company (APS) as Operating Agent and Agua Fria, LLC as Interconnection Customer. The filing was publicly noticed, and no protests or adverse comments were filed.

Key Takeaways:

  • The Arizona Public Service Company (APS) submitted an Engineering & Procurement Agreement (Agreement) on June 11, 2025, between APS as Operating Agent and Agua Fria, LLC as Interconnection Customer.
  • The Federal Energy Regulatory Commission accepted the submittal for filing, effective May 20, 2025, as requested.
  • The filing was publicly noticed, and no protests or adverse comments were filed.
  • Pursuant to Rule 214 of the Commission's regulations, notices of intervention, timely-filed motions to intervene, and unopposed motions to intervene out-of-time were granted.
  • This action does not constitute approval of any service, rate, charge, classification, or rule affecting such rate or service provided for in the filed document(s).
  • This order constitutes final agency action.
  • Requests for rehearing by the Commission may be filed within 30 days of the date of issuance of this order.

Statistics:

  • Date of issuance: August 4, 2025
  • Effective date: May 20, 2025
  • Document accession number: 20250804-3030
  • Filed date: August 4, 2025
  • Number of documents filed: 1 (ER25-2487-000.docx)

Sources:

1. FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, DC 20426 OFFICE OF ENERGY MARKET REGULATION Arizona Public Service Company Docket No. ER25-2487-000

2. 18 C.F.R. § 375.307, 18 C.F.R. § 385.214, 18 C.F.R. § 385.713, and 18 C.F.R. § 35.3(a)(2)