Federal Energy Regulatory Commission Issues Delegated Order on ISO New England and Connecticut Light and Power Company's Filing

The Federal Energy Regulatory Commission has issued a delegated order related to a non-conforming Standard Large Generator Interconnection Agreement submitted by ISO New England Inc. and The Connecticut Light and Power Company. The filing, accepted for public notice on May 12, 2022, was requested to be effective on April 12, 2022. The order grants notices of intervention and timely-filed motions to intervene, as well as any unopposed motions to intervene out-of-time filed before the issuance date of the order.

Key Takeaways:

  • The Federal Energy Regulatory Commission issued a delegated order on July 11, 2022, in response to a non-conforming Standard Large Generator Interconnection Agreement submitted by ISO New England Inc. and The Connecticut Light and Power Company.
  • The filing was accepted for public notice on May 12, 2022, with interventions and protests due on or before June 2, 2022.
  • The order grants notices of intervention and timely-filed motions to intervene, as well as any unopposed motions to intervene out-of-time filed before the issuance date of the order.
  • No protests or adverse comments were filed as a result of the public notice.
  • The action does not constitute approval of any service, rate, charge, classification, or any rule, regulation, contract, or practice affecting such rate or service provided for in the filed document(s).
  • Requests for rehearing by the Commission may be filed within 30 days of the date of issuance of this order, pursuant to 18 C.F.R. SS 385.713 (2021).

Statistics:

  • 1 non-conforming Standard Large Generator Interconnection Agreement submitted by ISO New England Inc. and The Connecticut Light and Power Company
  • 1 delegated order issued by the Federal Energy Regulatory Commission (FERC) on July 11, 2022
  • April 12, 2022: requested effective date for the filing
  • May 12, 2022: public notice of the filing
  • June 2, 2022: due date for interventions and protests
  • 30 days: timeframe for filing requests for rehearing with the Commission, pursuant to 18 C.F.R. SS 385.713 (2021)

Sources:

  • FERC Delegated Order issued on July 11, 2022, in Docket No. ER22-1862-000
  • 18 C.F.R. SS 385.713 (2021) - Rule regarding Rehearings