Federal Energy Regulatory Commission Issues Delegated Order on Tri-State Generation and Transmission Association's Revised Agreement

The Federal Energy Regulatory Commission (FERC) has issued a delegated order in response to a revised letter agreement filed by Tri-State Generation and Transmission Association, Inc. (Tri-State) on September 5, 2025. The agreement pertains to the Kinnan 115 - 34.5 kV Delivery Point between Tri-State and Wyrulec Company. After receiving the revised agreement, FERC accepted the submittal for filing, effective November 5, 2025, as requested by Tri-State. The filings were publicly noticed, and no protests or adverse comments were filed.

Key Takeaways:

  • The FERC has accepted the revised letter agreement filed by Tri-State on September 5, 2025, for the Kinnan 115 - 34.5 kV Delivery Point between Tri-State and Wyrulec Company.
  • The acceptance is effective November 5, 2025, as per Tri-State's request.
  • The filings were publicly noticed, and no protests or adverse comments were received from the public.
  • Pursuant to Rule 214 of the Commission's regulations, notices of intervention, timely filed motions to intervene, and any unopposed motions to intervene out-of-time filed before the issuance date of this order are granted.
  • This action does not constitute approval of any service, rate, charge, classification, or any rule, regulation, contract, or practice affecting such rate or service provided for in the filed documents.
  • Requests for rehearing by the Commission may be filed within 30 days of the date of issuance of this order, pursuant to 18 C.F.R. § 385.713.

Statistics:

  • 1 revised letter agreement was filed by Tri-State on September 5, 2025.
  • 1 delegated order was issued by the FERC on October 28, 2025.
  • The filed agreement pertains to the Kinnan 115 - 34.5 kV Delivery Point.
  • The acceptance is effective November 5, 2025.
  • No protests or adverse comments were received from the public.
  • 30 days have been allotted for requests for rehearing.

Sources:

  • Federal Energy Regulatory Commission
  • Tri-State Generation and Transmission Association, Inc.
  • Tri-State Wholesale Electric Service Contracts, Rate Schedule No. 375, Rate Schedule No. 375, Wyrulec (1.0.0)