Federal Energy Regulatory Commission Requests Additional Information from ANR Pipeline Company

The Federal Energy Regulatory Commission has issued a request for additional information from ANR Pipeline Company regarding its proposal to upgrade its facilities. The Commission has asked ANR Pipeline to provide detailed information about the estimated first-year cost of service of $160,234,145 and to clarify the system rates for comparison against the proposed FTS-1 rates. The request is part of the Commission's analysis of ANR Pipeline's application and requires the company to file a response within five business days.

Key Takeaways:

  • The Federal Energy Regulatory Commission has issued a request for additional information from ANR Pipeline Company regarding its proposal to upgrade its facilities.
  • The Commission has asked ANR Pipeline to provide detailed information about the estimated first-year cost of service of $160,234,145, specifically whether it includes any costs associated with the replacement facilities.
  • The Commission has also requested clarification on system rates for comparison against the proposed FTS-1 rates by zone, as reflected in line items 62 and 63.
  • The response must be filed within five business days from the date of the issuance of the letter.
  • The response must be filed electronically via the eFiling link on the Commission's web site at http://www.ferc.gov.
  • The response must be filed under oath by an authorized ANR Pipeline representative and include the name, position, and telephone number of the respondent to each item.

Statistics:

  • Estimated first-year cost of service: $160,234,145
  • Number of business days for response: 5
  • Date of issuance of the letter: August 5, 2025
  • Docket number: CP25-79-000

Sources:

  • FEDERAL ENERGY REGULATORY COMMISSION (2025, August 5). Letter Order Pursuant to SS 375.307. ANR Pipeline Company. Docket No. CP25-79-000.