US-based construction and construction materials company Granite has commenced work on a multi-million dollar project with San Francisco International Airport, a key component of the airport's multi-billion dollar Capital Improvement Program. The project involves the rehabilitation of Runway 1R-19L and the construction of Taxiway W, including upgrades to pavement, lighting, drainage, and signage. The project is expected to begin in March 2026 and continue through November 2026, with a total anticipated construction value of USD 115 million.
Key Takeaways:
- The project is a key component of San Francisco International Airport's multi-billion dollar Capital Improvement Program, aimed at modernizing and improving the airport's infrastructure.
- The project will rehabilitate Runway 1R-19L and construct Taxiway W, including upgrades to pavement, lighting, drainage, and signage.
- The existing Taxiway F1 will be demolished, and a new Taxiway W will be constructed.
- Granite will supply asphalt from its Santa Clara Asphalt facility, approximately 185,000 tons of P401 and P403 Mix.
- The project has a total anticipated construction value of USD 115 million.
- Granite will work as the Construction Manager/General Contractor (CM/GC) for the project.
- The project is expected to begin in March 2026 and continue through November 2026.
Statistics:
- Total anticipated construction value: USD 115 million.
- Number of tons of asphalt to be supplied by Granite: approximately 185,000 tons of P401 and P403 Mix.
- Project timeline:
+ Preconstruction: June 2025 through January 2026
+ Major Construction: March 2026 through November 2026