Great Lakes Gas Transmission Company has submitted supplemental information to the Federal Energy Regulatory Commission regarding its Farwell Compressor Station Project. The filing, dated October 28, 2025, is a response to a request from Commission staff for additional information to support the company's Advance Notification of Natural Gas Facilities Replacement, filed on October 1, 2025. The supplemental information is marked "Contains Critical Energy Infrastructure Information - Do Not Release" and is sought to be treated as confidential energy infrastructure information (CEII) under 18 C.F.R. § 388.113.

Key Takeaways:

  • Great Lakes Gas Transmission Company filed an Advance Notification of Natural Gas Facilities Replacement for the Farwell Compressor Station Project on October 1, 2025.
  • The company submitted supplemental information on October 28, 2025, in response to a request from Commission staff, which includes specific engineering, vulnerability, or detailed design information about existing critical infrastructure.
  • The supplemental information is marked "Contains Critical Energy Infrastructure Information - Do Not Release" and is sought to be treated as CEII for as long as the subject facilities are in service.
  • The company is e-filing the supplemental information in accordance with the Commission's Order No. 703, Filing Via the Internet guidelines, issued in Docket No. RM07-16-000 on November 15, 2007.
  • Great Lakes requests that the attachment submitted herein be accorded CEII treatment pursuant to 18 C.F.R. § 388.113 of the Commission's regulations.
  • The undersigned, LaShawndra R. Proctor, Manager, Project Authorizations, certifies that she has read the filing and knows its contents, and that the contents are true as stated to the best of her knowledge, information, and belief based on representations by the company's personnel.

Statistics:

  • Great Lakes Gas Transmission Company submitted the supplemental information on October 28, 2025.
  • The company filed the Advance Notification of Natural Gas Facilities Replacement on October 1, 2025.
  • The subject facilities will be treated as CEII for as long as they are in service.
  • The Commission's Order No. 703, Filing Via the Internet guidelines, was issued in Docket No. RM07-16-000 on November 15, 2007.

Sources:

*

Great Lakes Gas Transmission Company. (October 28, 2025). Re: Great Lakes Gas Transmission Company Docket No. CP26-1-000 Farwell Compressor Station Project Supplemental Information. Federal Energy Regulatory Commission. https://elibrary.ferc.gov