Illinois Commerce Commission Approves Time Extension for Highway-Rail Grade Crossing Improvement Project
The Illinois Commerce Commission has approved a time extension for a highway-rail grade crossing improvement project in Cumberland County, Illinois. The project, involving CSX Transportation, Inc., the Crooked Creek Township Road District, the Cumberland County Highway Department, and the Illinois Department of Transportation, aims to improve public safety at two highway-rail grade crossings. The original deadline for completion was July 3, 2025, but due to delays caused by wet weather, the parties requested an extension until November 30, 2025.
Key Takeaways:
- The Illinois Commerce Commission has approved a time extension for a highway-rail grade crossing improvement project in Cumberland County, Illinois, from July 3, 2025, to November 30, 2025.
- The project involves CSX Transportation, Inc., the Crooked Creek Township Road District, the Cumberland County Highway Department, and the Illinois Department of Transportation.
- The extension was granted due to delays caused by wet weather, IDOT's environmental review and approval process, and CSX's lead time for acquiring, installing, and testing hydrogen fuel cells for emergency power.
- The original deadline for completion was set by the Commission's Order entered on January 3, 2024, requiring the project to be completed within 18 months.
- The parties involved, including CSX and the County/Township, noted that the delays have caused significant financial and logistical challenges.
- The Commission's approval of the time extension allows the parties to continue with the project, which aims to improve public safety at two highway-rail grade crossings.
Statistics:
- Deadline for completion: July 3, 2025 (original), November 30, 2025 (extended)
- Number of highway-rail grade crossings involved: 2
- Number of parties involved: 4 (CSX Transport, Inc., Crooked Creek Township Road District, Cumberland County Highway Department, and Illinois Department of Transportation)
- Length of extension: 4.5 months
- Percentage of project completion: 0% (no data provided)
Sources:
- Illinois Commerce Commission (July 17, 2025): "Docket Number: T23-0111 ROM Date: 07/17/2025 Deadline: N/A M E M O R A N D U M"
- Illinois Commercial Transportation Law: Section 18c-7401
- Commission's Order: January 3, 2024
- County/Township Petition: May 19, 2025
- CSX Petition: June 10, 2025