The New York State Public Service Commission is holding virtual public statement hearings to discuss the proposed transfer of ownership of the Indian Point nuclear power plant from Entergy Corporation to Holtec International. The transfer, which would include the three power reactors, spent fuel pools, and various support facilities, has sparked concern among local residents and environmental groups. The hearings will provide an opportunity for the public to comment on the proposed transaction, with several options available for those who wish to participate.

Key Takeaways:

  • The proposed transfer of ownership of the Indian Point nuclear power plant from Entergy Corporation to Holtec International has sparked concern among local residents and environmental groups.
  • The transfer would include the three power reactors, spent fuel pools, and various support facilities, with Holtec assuming responsibility for site restoration, decommissioning, and spent fuel management activities.
  • The New York State Public Service Commission has issued a notice inviting public comment on the proposed transaction, with several options available for those who wish to participate.
  • Virtual public statement hearings will be held on February 23, 2021, at 1:00 PM and 6:00 PM, with a livestream available on the Department of Public Service YouTube channel.
  • Individuals can register to speak at the hearings electronically or by phone, with written comments also accepted.
  • The Commission may adopt, reject, or modify the proposed action, with a verbatim transcript of the hearings available for inclusion in the record of the case.

Statistics:

  • The Indian Point nuclear power plant has three power reactors and several support facilities.
  • The proposed transfer of ownership would transfer the site, spent fuel, and waste storage facilities, together with certain other assets and liabilities, from Entergy to Holtec.
  • The Commission has scheduled two virtual public statement hearings on February 23, 2021, at 1:00 PM and 6:00 PM.
  • Registration for the hearings is required, either electronically or by phone, to provide a statement on the record.
  • The Commission will consider written comments, which must be submitted by 5:00 PM on Friday, February 26, 2021.

Sources:

  • New York Public Service Commission, Case 19-E-0730: Joint Petition of Entergy Nuclear Indian Point 2, LLC; Entergy Nuclear Indian Point 3, LLC; and Nuclear Asset Management Company, LLC for a Declaratory Ruling Disclaiming Jurisdiction Over or Abstaining from Review of the Proposed Transfers or, in the Alternative, an Order Approving the Proposed Transfers Pursuant to Section 70 of the New York Public Service Law. NOTICE OF PUBLIC STATEMENT HEARINGS (Issued February 12, 2021)
  • New York Public Service Commission, Case 19-E-0730: Public Notice (Published in the January 29, 2020 edition of the State Register, page 27-28)
  • New York Public Service Commission, Case 19-E-0730: Notice of Virtual Public Statement Hearings (Issued February 12, 2021)