Lanzhou: Pingliang City Enhances Urban Flood Prevention Measures
In response to frequent extreme weather events, Pingliang City has taken proactive measures to strengthen its urban flood prevention work. The Municipal Housing and Urban-Rural Development Bureau has coordinated with city and county levels to focus on daily prevention, hidden danger inspections, and on-duty work. This includes conducting comprehensive risk assessments, formulating targeted preventive measures, and addressing potential hazards through engineering measures.
Key Takeaways:
- The city has organized dedicated working groups to supervise and guide all counties in conducting comprehensive risk assessments of flood-prone areas, including low-lying urban areas, construction sites, and underground garages.
- The city has formulated targeted preventive measures, including dredging and maintenance of municipal stormwater facilities, inspecting and clearing stormwater and sewage pipes, and replacing manhole covers and rainwater grates.
- Engineering measures have remediated seven potential urban waterlogging sites, eliminating 132 potential disaster-related hazards associated with municipal infrastructure.
- The city has intensified spot checks and reviews of emergency response plans for 14 projects in the construction phase, issued 43 rectification notices, and rectified 217 safety hazards.
- The flood control system has been continuously improved, with construction commenced on six urban drainage and flood control projects, and 10.25 kilometers of stormwater pipes renovated.
- The city has made significant progress in systematic flood control, and will continue to tighten the duty system, enforce strict work discipline, and maintain a high degree of vigilance.
Statistics:
- 324 kilometers of stormwater and sewage pipes were inspected and cleared
- 4,823 inspection wells and 7,321 rainwater collection points were cleaned and repaired
- 189 manhole covers and 266 rainwater grates were replaced
- 14 projects in the construction phase were subject to intensified spot checks and reviews
- 43 rectification notices were issued
- 217 safety hazards were rectified
- 10.25 kilometers of stormwater pipes were renovated
- 237 inspection wells and stormwater grates were installed