National Fuel Gas Supply Corporation Submits Weekly Environmental Status Report
National Fuel Gas Supply Corporation has submitted a report to the Federal Energy Regulatory Commission regarding its Line UNY Westwood 2025 Modernization Project. The report outlines the company's environmental efforts and construction progress from June 1 to 7, 2025.
The report highlights several key developments, including the completion of environmental training for 51 company personnel and contractors, the installation of timber mat access roads, and the commencement of boring operations under Pleasant View Drive. Additionally, the report notes that there were no instances of environmental non-compliance during the reporting period and no correspondence received from other permitting agencies regarding compliance.
Key Takeaways:
- 51 company personnel and contractors have completed environmental training.
- Timber mat access roads have been installed, and perimeter controls have been installed from 132+00 to 124+00.
- Boring operations have commenced under Pleasant View Drive and Middlebury Lane.
- All 7 stream/waterbody crossings have yet to be completed.
- There have been no instances of environmental non-compliance during this reporting period.
Statistics:
- 51 company personnel and contractors have completed environmental training (100% of training attendees).
- 64% of clearing has been completed.
- Grading and trenching are at 61% and 8%, respectively.
- Welding, lowering-in, and backfilling are at 14%, 8%, and 8%, respectively.
- Restorative seeding and mulching have not commenced (0% complete).
- Winterization is not applicable (0% complete).
Sources:
- National Fuel Gas Supply Corporation Line UNY Westwood 2025 Modernization Project Docket No. CP25-22-000 Weekly Environmental Inspection Report (Reporting Period: 06/01/25 through 06/07/25).