The National Grid Company of Pakistan Ltd. (NGC) has made a significant advancement in Pakistan's power infrastructure by successfully energizing the 500 kV K2/K3-Matiari and KKI-Port Qasim transmission line circuits. The 102 km transmission line is designed to evacuate 2,200 MW of power from the K2 and K3 nuclear power plants near Karachi, creating a dedicated link between the K2/K3 facilities of KANUUP (PAEC) and the existing 500 kV Port Qasim - Matiari transmission line. Completed at an estimated cost of PKR 18.45 billion, the project enhances the reliability, stability, and capacity of the national grid.

Key Takeaways:

  • The NGC has successfully energized the 500 kV K2/K3-Matiari and KKI-Port Qasim transmission line circuits, marking a significant advancement in Pakistan's power infrastructure.
  • The 102 km transmission line is designed to evacuate 2,200 MW of power from the K2 and K3 nuclear power plants near Karachi.
  • The project was completed at an estimated cost of PKR 18.45 billion and involves the dedication of the Ministry of Energy (Power Division), the Board of Directors of NGC, and various NGC departments.
  • The project enhances the reliability, stability, and capacity of the national grid and increases the grid's resilience in the southern region.
  • The energization of the transmission line is expected to spur regional development and job creation while supporting economic growth.
  • The project aligns with Pakistan's energy security goals by integrating clean nuclear energy into the national energy mix.
  • Engr. Muhammad Shahid Nazir, Managing Director of NGC, commended the teams involved for their dedication and emphasized the company's commitment to enhancing Pakistan's transmission capabilities.

Statistics:

  • 102 km: Length of the 500 kV K2/K3-Matiari and KKI-Port Qasim transmission line circuits.
  • 2,200 MW: Power evacuation capacity of the transmission line from the K2 and K3 nuclear power plants near Karachi.
  • PKR 18.45 billion: Estimated cost of the project.
  • 500 kV: Voltage of the transmission line.

Sources:

  • PPI-PR: National Grid Company of Pakistan Ltd. successfully energizes 500 kV transmission lines.