NYSDEC Supports Temporary Variance for Hudson River Hydroelectric Project
The New York State Department of Environmental Conservation (NYSDEC) has submitted comments to the Federal Energy Regulatory Commission (FERC) in support of a temporary variance for the Hudson River Hydroelectric Project at the Spier Falls Development. The project, located in Saratoga and Warren Counties, has been affected by a fire in the Spier Falls powerhouse, which resulted in both generating units falling out of service. In response, the Applicant, Erie Boulevard Hydropower, LP, has requested a temporary variance from the reservoir elevation requirements to facilitate repairs. NYSDEC has reviewed the application and recommends that the impoundment be refilled at no more than 1-foot per hour to prevent contravention of New York State water quality standards and reduce the risk of erosion.
Key Takeaways:
- NYSDEC has reviewed the Notice of Application Ready for Temporary Variance Accepted for Filing and Soliciting Comments, Motions to Intervene, and Protests for the Hudson River Hydroelectric Project, FERC No. P-2482.
- The Applicant, Erie Boulevard Hydropower, LP, has requested a temporary variance from the reservoir elevation requirements to facilitate repairs at the Spier Falls powerhouse due to a fire on September 14, 2024.
- NYSDEC recommends that the impoundment be refilled at no more than 1-foot per hour to prevent contravention of New York State water quality standards and reduce the risk of erosion.
- The impoundment was lowered to the spillway crest elevation of 428.8 feet, or six feet below the lower impoundment level, on October 9, 2024, following consultation with NYSDEC.
- The Applicant estimates that the powerhouse reconstruction will take more than a year to complete, and it is estimated that the impoundment will be refilled by October 2025.
- NYSDEC does not oppose the Applicant's request for the temporary variance to remain in effect until October 30, 2025.
Statistics:
- The Spier Falls powerhouse caught fire on September 14, 2024.
- The impoundment was lowered to the spillway crest elevation of 428.8 feet, or six feet below the lower impoundment level, on October 9, 2024.
- The Applicant estimates that the powerhouse reconstruction will take more than a year to complete.
- It is estimated that the impoundment will be refilled by October 2025.
- The temporary variance is requested to remain in effect until October 30, 2025.
Sources:
- New York State Department of Environmental Conservation (2025, August 26). Division of Environmental Permits 625 Broadway Albany, NY 12233-1750 | dec.ny.gov | hydro@dec.ny.gov | (518) 402-9167.
- Erie Boulevard Hydropower, LP (2024, October 6). FERC Accession #: 20241007-5019.
- Erie Boulevard Hydropower, LP (2025, June 10). FERC Accession #: 20240610-5021.