Pacific Gas and Electric Company Requests Extension of Time for Potable Water Signage Action at Bucks Creek Hydroelectric Project

The Federal Energy Regulatory Commission (FERC) conducted an environmental inspection of the Bucks Creek Hydroelectric Project in September 2025, resulting in eight follow-up action items. The Pacific Gas and Electric Company (PG&E) has submitted a request for an extension of time to address FERC's follow-up Action Item 3, which requires the installation of potable water signs at affected campgrounds. PG&E proposes to install the required signage upon facility reopening, weather permitting, and submit photo documentation by July 1, 2026.

Key Takeaways:

  • PG&E has requested an extension of time to complete the potable water signage action by July 1, 2026, due to the winterization of recreation facilities and the subsequent preparation for reopening.
  • The company proposes to install the required signage upon facility reopening, weather permitting, and submit photo documentation by July 1, 2026.
  • The potable water signage action is necessary to ensure that the public is aware of the water quality issues and safe and unsafe uses of the water at the campgrounds.
  • PG&E is committed to addressing the issue and working towards providing potable water at all recreation facilities.
  • The company will continue to update and change the signs as water supply repairs are completed and water quality testing informs potable water safety.

Statistics:

  • 8 follow-up action items resulting from the FERC environmental inspection of the Bucks Creek Hydroelectric Project.
  • 3 specific action items requiring attention from PG&E.
  • July 1, 2026, proposed completion date for the potable water signage action.
  • 7 days timeframe for PG&E to complete the potable water signage action as per FERC's original request.
  • 2023, the year in which Bucks campgrounds did not begin to open until July 1 due to lingering snowpack.

Sources:

  • Pacific Gas and Electric Company (PG&E) letter to Federal Energy Regulatory Commission (FERC) dated October 16, 2025.
  • Federal Energy Regulatory Commission (FERC) letter to Pacific Gas and Electric Company (PG&E) dated October 9, 2025.
  • Extension of Time Request for follow-up Action Item 3 ENCLOSURE 1 1 Bucks Creek Hydroelectric Project, FERC No. 619-CA October 8, 2025.