PETRONAS Gas Bhd Restores Natural Gas Supply and Enhances Safety Measures in Malaysia
PETRONAS Gas Bhd (PGB) has successfully restored natural gas supply to Batu Tiga, Shah Alam, and Connaught Bridge following the commissioning of its newly constructed bypass pipeline on July 1, 2025. The company emphasized its commitment to safe, reliable energy for all, with natural gas powering between 40% to 50% of Malaysia's electricity. As part of its safety-first philosophy, PGB has implemented enhanced engineering reinforcements at the bypass section in Putra Heights, including advanced sensors to detect soil and pipe movement, exceeding standard requirements.
Key Takeaways:
- PGB restored natural gas supply to Batu Tiga, Shah Alam, and Connaught Bridge following the commissioning of its newly constructed bypass pipeline on July 1, 2025.
- The company fulfilled all engineering, operational, and regulatory safety requirements, including the issuance of a permit to operate (PTO) by the Occupational Safety and Health Department (DOSH).
- PGB implemented enhanced engineering reinforcements at the bypass section in Putra Heights, including advanced sensors to detect soil and pipe movement, exceeding standard requirements.
- The company installed sheet piling and engineered support structures to safeguard the pipeline, ensuring safe, secure, and uninterrupted performance.
- A new permanent pipeline is currently being designed with enhanced safety features and will be installed on deep-piled slab foundations, offering greater structural resistance to soil movement and unpredictable ground shifts.
- PGB disbursed more than RM2 million in ex-gratia and humanitarian aid through local authorities, including RM1.38 million in direct assistance to affected families and a RM25 million contribution via the Housing and Local Government Ministry for home reconstruction.
- The company carried out precautionary assessments along other sections of the 2,680-kilometre Peninsular Gas Utilisation (PGU) pipeline to ensure system-wide integrity.
Statistics:
- The newly constructed bypass pipeline is part of the 2,680-kilometre Peninsular Gas Utilisation (PGU) pipeline.
- PGB disbursed RM1.38 million in direct assistance to affected families.
- The company provided a RM25 million contribution via the Housing and Local Government Ministry for home reconstruction.
- A total of RM2 million was disbursed in ex-gratia and humanitarian aid through local authorities.
Sources:
- BERNAMA News Agency (July 7, 2025)
- PETRONAS Gas Bhd (no date specified)