PJM Interconnection Extends Milestone Dates for New Road Power, LLC
PJM Interconnection, L.L.C. has entered into a Service Agreement with New Road Power, LLC and Virginia Electric and Power Company for interconnection services. However, due to delays caused by the Interconnected Transmission Owner's delivery of breakers, the Interconnection Customer encountered difficulties. Pursuant to Section 6.0 of the Service Agreement, PJM has reasonably determined that the Interconnection Customer did not cause the delay and could not remedy it through the exercise of due diligence. As a result, PJM is extending the project-specific milestones for the Service Agreement.
Key Takeaways:
- PJM Interconnection, L.L.C. has submitted a document to the Federal Energy Regulatory Commission to extend milestone dates for the Service Agreement with New Road Power, LLC and Virginia Electric and Power Company.
- The delay was caused by the Interconnected Transmission Owner's delivery of breakers, and PJM has reasonably determined that the Interconnection Customer did not cause the delay and could not remedy it through due diligence.
- Section 6.0 of the Service Agreement provides for the extension of milestone dates in such cases.
- The project-specific milestones have been extended as follows:
+ Section 6.3: Original date August 1, 2026; new date April 28, 2027.
+ Section 6.4: Original date August 1, 2026; new date April 28, 2027.
+ Section 6.5: Original date December 31, 2026; new date September 27, 2027.
- The Service Agreement has been modified to reflect the changes in milestone dates.
- The Parties have authorized PJM to file the amended Service Agreement and the Milestone Change Document with the Federal Energy Regulatory Commission without requiring additional signatures.
Statistics:
- Original milestone date for section 6.3: August 1, 2026.
- New milestone date for section 6.3: April 28, 2027.
- Original milestone date for section 6.4: August 1, 2026.
- New milestone date for section 6.4: April 28, 2027.
- Original milestone date for section 6.5: December 31, 2026.
- New milestone date for section 6.5: September 27, 2027.
Sources:
- PJM Interconnection, L.L.C. (2023). Executed Milestone Change Document. Docusign Envelope ID: F392CD57-3F06-41D5-81FC-8913AB15226D.