President Marcos Optimistic on Finding More Gas Reserves at Malampaya Field

President Ferdinand Marcos expressed confidence in discovering additional gas reserves at the Malampaya gas field as the ongoing drilling operations under Phase 4 of the project near Palawan enter a critical phase. Energy Secretary Sharon Garin confirmed that the $893-million project to extend the life of the Malampaya gas field is on track for completion this year, with a reasonable chance of success in finding further reserves. The drilling operation involves exploring two new deep-water wells, Camago-3 and Malampaya East-1, as well as a new exploration field, Bagong Pag-asa-1. The Malampaya gas field is the country's only indigenous gas source, supplying approximately 20% of Luzon's electricity needs, albeit at a reduced capacity of 1.2 to 1.3 GW due to declining reserves.

Key Takeaways:

  • The ongoing drilling operations under Phase 4 of the Malampaya project near Palawan are expected to explore the potential for additional gas reserves.
  • Energy Secretary Sharon Garin stated that the $893-million drilling project is on track for completion this year, with a reasonable chance of success.
  • The project involves drilling two new deep-water wells, Camago-3 and Malampaya East-1, as well as a new exploration field, Bagong Pag-asa-1.
  • The Malampaya gas field is the country's only indigenous gas source, supplying approximately 20% of Luzon's electricity needs.
  • The current output of Malampaya is 1.2 to 1.3 GW, below its former output due to declining reserves, with the goal of boosting production to 1.5 to 1.7 GW.
  • The project is operated by Razon-led Prime Energy Resources Development and its partners, UC38 LLC, PNOC Exploration Corp., and Prime Oil and Gas Inc.

Statistics:

  • $893 million: The project's estimated cost for extending the life of the Malampaya gas field.
  • 20%: The percentage of Luzon's electricity needs supplied by the Malampaya gas field.
  • 1.2-1.3 GW: The current output of Malampaya, below its former output due to declining reserves.
  • 1.5-1.7 GW: The goal of boosting Malampaya's natural gas production.
  • February 2039: The extended contractual lifetime of the Malampaya gas field based on the Renewal Agreement of Service Contract No. 38 (SC 38).
  • February 2024: The original contract expiration date for the Malampaya gas field.

Sources:

  • Garin, S. (2023). Interview with the President.
  • Marcos, F. (2023). Groundbreaking ceremony for the P2.5-billion Caticlan Passenger Terminal Building at the Caticlan Airport in Aklan.
  • Department of Energy. (2023). Renewal Agreement of Service Contract No. 38 (SC 38).