Progress on Urban Mobility Service Improvement in Ilo Generates Job Opportunities

The Provincial Municipality of Ilo, led by Mayor ABG Humberto Tapia Garay, is making significant strides in improving the urban mobility service on local roads in the San Pedro Upis Alto Ilo sector. The project, which has been long-awaited by neighbors for over 30 years, is expected to benefit the population with an approximate investment of 3 million 500 thousand soles and a duration of 180 calendar days. As of now, the work is 12% complete, with demolition of rigid and flexible pavement on tracks and paths of streets 11, 12, 13, 14, 16, and 17 already done, except for the intervention on 24th street. The project uses a combination of municipal and private operators, with 20 workers currently involved, including labor and administrative staff.

Key Takeaways:

  • The urban mobility service improvement project is expected to be completed within 180 calendar days with an approximate investment of 3 million 500 thousand soles.
  • The project is 12% complete, with demolition work already done on streets 11, 12, 13, 14, 16, and 17.
  • The project uses 20 workers, including labor and administrative staff, and is expected to create five more direct jobs for sector residents in the coming days.
  • The work involves formwork and emptying, vertical and horizontal signage, and other technical aspects to guarantee the functionality and safety of the new paths.
  • The project is part of Mayor ABG Humberto Tapia Garay's efforts to modernize Ilo and improve the quality of life of its inhabitants.
  • The project aims to favor urban mobility, road safety, and the improvement of the quality of life of the inhabitants.

Statistics:

  • 180 calendar days: duration of the project
  • 3 million 500 thousand soles: approximate investment for the project
  • 20 workers: current number of labor and administrative staff involved in the project
  • 5 workers: additional direct jobs expected to be created for sector residents in the coming days
  • 12%: progress made on the project
  • 6 streets (11, 12, 13, 14, 16, 17): completion of demolition work on tracks and paths
  • 1 street (24th): remaining intervention to be completed on the project