Public Utility Commission of Texas Approves Fagus Solar's PGC Registration Amendment

The Public Utility Commission of Texas (PUCT) has approved an amendment to Fagus Solar's power generation company (PGC) registration on July 18, 2025. Fagus Solar, a PGC registered with the Federal Energy Regulatory Commission (FERC) as an exempt wholesale generator, submitted an amendment to its PGC registration on July 10, 2025, to reflect its revised status. The PUCT's staff recommendation, submitted by James Kelsaw, Consumer Protection Division, concluded that Fagus Solar had met the necessary registration requirements.

Key Takeaways:

  • Fagus Solar submitted an amendment to its PGC registration on July 10, 2025, to reflect its updated status as an exempt wholesale generator with the FERC.
  • The amendment was reviewed by James Kelsaw, Consumer Protection Division, who concluded that Fagus Solar had satisfactorily completed the registration requirements.
  • The PUCT's staff recommendation was to approve Fagus Solar's amendment request and update the commission's records.
  • Fagus Solar's PGC registration number is 20952, and its FERC registration will be revised to reflect the amendment.
  • The PUCT's approval requires Fagus Solar to report changes in information within 30 days and sign an oath or affirmation to comply with 16 Texas Administrative Code (TAC) §25.109.
  • This approval has implications for the Texas energy market, as Fagus Solar will now be recognized as an exempt wholesale generator under FERC regulations.

Statistics:

  • Registration number: 20952
  • Date of amendment submission: July 10, 2025
  • Date of PUCT approval: July 18, 2025
  • Timeframe for reporting changes: 30 days

Sources:

  • Public Utility Commission of Texas Memorandum (no date issues)
  • 16 Texas Administrative Code (TAC) §25.109 (no date issues)