Public Utility Commission of Texas Orders Jaguar Solar to Correct Application or Withdraw
The Public Utility Commission of Texas (PUCT) has issued an order requiring Jaguar Solar Owner 2024, LLC to correct its application to amend its renewable energy credit microgenerator aggregator registration. The application was filed on April 15, 2025, but was found to contain an incorrect document, which was later omitted from the filing. Despite a deadline set by the administrative law judge, Jaguar Solar has not taken corrective action, prompting the PUCT to issue a revised deadline for correction or withdrawal of the application.
Key Takeaways:
- The Public Utility Commission of Texas (PUCT) has ordered Jaguar Solar Owner 2024, LLC to correct its application to amend its renewable energy credit microgenerator aggregator registration.
- The application was filed on April 15, 2025, but contained an incorrect document that was later omitted from the filing.
- Jaguar Solar was required to clarify its filings and submit a corrected application by May 30, 2025, but failed to do so.
- The PUCT has issued a revised deadline for Jaguar Solar to file a corrected application in the docket by June 20, 2025.
- Alternatively, Jaguar Solar may withdraw its application.
- The Director of the Public Utility Commission of Texas is Isaac Ta.
- The document attached to the order is dated June 5, 2025.
Statistics:
- The filing date for Jaguar Solar's original application was April 15, 2025.
- The deadline for Jaguar Solar to clarify its filings and submit a corrected application was May 30, 2025.
- The revised deadline for Jaguar Solar to file a corrected application is June 20, 2025.
- The order was signed by Isaac Ta, Administrative Law Judge, on June 5, 2025.
Sources:
- Document attached to the order: "\puc4avfs\shared\cadm\docket management\electric\microgenerator aggregator\57965-2 reg clarif.docx"
- Public Utility Commission of Texas