Puget Sound Energy's Baker River Hydroelectric Project Experiences Instream Flow and Downramping Rate Deviation on July 16, 2025

On July 16, 2025, Puget Sound Energy's (PSE) Baker River Hydroelectric Project experienced a deviation from the minimum instream flow (MIF) and downramping rate requirements. The incident occurred when Unit 3 tripped offline due to a loss of station service caused by a bird electrocution, resulting in a 3,200 cfs discharge drop to 564 cfs. The synchronous bypass valve (SBV) took 14 minutes to fully react, and Unit 4 failed to start automatically due to a stuck wicket gate. The deviation lasted for 14 minutes, during which the plant discharge was below the MIF requirement.

Key Takeaways:

  • The Baker River Hydroelectric Project has a minimum instream flow (MIF) requirement of 1,200 cfs between October 21 and July 31, as specified in settlement agreement article (SA) 106, aquatics table 1, in appendix A of the Project's license.
  • The MIF deviation occurred on July 16, 2025, when Unit 3 tripped offline and the synchronous bypass valve (SBV) took 14 minutes to fully react, resulting in a drop to 564 cfs.
  • Unit 4 failed to start automatically due to a stuck wicket gate, which is attributed to the gate getting stuck.
  • A repair plan is underway to address the slow response of the SBV, which may have been caused by corrosion in the valve.
  • The incident resulted in a 14-minute deviation from the MIF requirement, during which the plant discharge was below the required 1,200 cfs.
  • The Baker Aquatic Resources Group (ARG) was notified via e-mail regarding the potential downramping rate deviation, but no comments were received.
  • PSE has scheduled its annual outage for September to address the wicket gate issue and fix it by then.

Statistics:

  • The minimum instream flow (MIF) requirement at the Baker River Hydroelectric Project is 1,200 cfs between October 21 and July 31.
  • The discharge at Lower Baker was 3,200 cfs when Unit 3 tripped offline on July 16, 2025.
  • The synchronous bypass valve (SBV) took 14 minutes to fully react during the incident.
  • The 15-minute drop at the USGS gage downstream was 2.13 feet from 01:15 to 01:30.
  • The hour-to-hour drop was 1.47 feet from 01:15 to 02:15.
  • The lowest flow at the USGS gage downstream was 564 cfs.
  • The average of the 15-minute flow readings for the 01:00 to 01:45 hour at the Plant was 910 cfs, which is below the MIF requirement.

Sources:

  • Puget Sound Energy, INC. (2025) Federal Energy Regulatory Commission Mail Code: DHAC, PJ-12 888 First Street, NE Washington, DC 20426 Re: Follow-up Letter for a Potential Minimum Instream Flow and Downramping Rate Deviation on July 16, 2025.
  • 125 FERC P 62,064 (2008)