Quadvest's Response to Public Utility Commission of Texas: Overview of Water and Sewer Service Proposal

The Public Utility Commission of Texas (PUC) has received a document from Quadvest, L.P. (Quadvest) in response to the Commission's Third Request for Information. The submission, dated June 23, 2025, addresses the infrastructure requirements for providing water and sewer service to the requested area in Waller County, Texas. Quadvest has submitted a comprehensive plan detailing capital improvements, timelines, and financial commitments necessary to install the necessary infrastructure.

Key Takeaways:

  • Quadvest has submitted detailed capital improvement plans for water distribution lines, sewer collection lines, and connections costs, which are required to provide full water and sewer service to the requested area.
  • The plans are presented on a timeline for installation, as per the Texas Water Commission (TWC) regulations under Section 13.244(d) and 16 TAC Section 24.233(a).
  • Quadvest has provided fully executed firm capital commitments, including proof of access to sufficient cash reserves, line of credit, and loan approval documents, to demonstrate their ability to fund the capital improvements.
  • Alternatively, Quadvest has offered to provide a written guaranty to fund the capital improvements using their excess cash reserves and line of credit funding.
  • The submission includes an attached confidential exhibit (Exhibit A) containing the requested information responsive to STAFF RFI 3-1 and STAFF RFI 3-2.
  • The proposal aims to provide continuous and adequate service to the requested area, with a focus on infrastructure development and financial commitments to support the project.

Statistics:

  • The requested area in Waller County, Texas, requires capital improvements for water distribution lines, sewer collection lines, and connections costs.
  • The estimated timeline for installation of the capital improvements is not specified.
  • Quadvest has provided fully executed firm capital commitments to demonstrate $X amount of funding available for the project.
  • The written guaranty offered by Quadvest will utilize their excess cash reserves and line of credit funding, totaling $Y amount.

Sources:

  • Document from Quadvest, L.P. to Public Utility Commission of Texas, DOCKET NO. 54841.
  • Texas Water Commission (TWC) regulations under Section 13.244(d) and 16 TAC Section 24.233(a).