Revisions to Attachment H-9A of PJM Tariff Accepted for Filing
Pursuant to an agreement reached between Southern Maryland Electric Cooperative (SMECO) and Potomac Electric Power Company (Pepco), the Federal Energy Regulatory Commission (FERC) has accepted for filing revisions to Attachment H-9A of the PJM Open Access Transmission Tariff (PJM Tariff). The revisions, which were submitted by Pepco on March 25, 2015, aim to effectuate the agreement reached with SMECO regarding the treatment of certain costs in the 2014 Annual Formula Rate Update. The filing was noticed on March 25, 2015, with comments, interventions, and protests due on or before April 15, 2015.
Key Takeaways:
- The revisions to Attachment H-9A were submitted by Potomac Electric Power Company (Pepco) on March 25, 2015, for the limited purpose of effectuating an agreement reached with Southern Maryland Electric Cooperative (SMECO).
- The revisions were accepted for filing by the Federal Energy Regulatory Commission (FERC) on April 27, 2015, as part of Docket No. ER15-1374-000.
- The agreement between Pepco and SMECO concerns the treatment of certain costs in the 2014 Annual Formula Rate Update.
- The filing was noticed on March 25, 2015, with comments, interventions, and protests due on or before April 15, 2015.
- The acceptance of the revisions does not constitute approval of the filing or any rate, charge, classification, or practice affecting such rate or service contained in the filing.
- The acceptance is without prejudice to any findings or orders that have been or may hereafter be made by the Commission in any proceeding now pending or hereafter instituted by or against Pepco.
Statistics:
- The revisions to Attachment H-9A were submitted on March 25, 2015.
- The filing was noticed on March 25, 2015.
- Comments, interventions, and protests were due on or before April 15, 2015.
- The revisions were accepted for filing on April 27, 2015.
- Docket No. ER15-1374-000 is associated with the revisions to Attachment H-9A.
- The Commission will consider requests for rehearing of the order within 30 days of issuance.
Sources:
- Federal Energy Regulatory Commission, "Docket No. ER15-1374-000"
- 18 C.F.R. § 385.214, "Rule 214"
- 18 C.F.R. § 385.713, "Requests for Rehearing"