Stop Lava Ridge, Inc. Seeks to Protest SWIP-N Transmission Line Amidst Government Policy Shifts and Environmental Concerns
Stop Lava Ridge, Inc., a coalition of farmers, ranchers, and community members, has filed a motion to protest the Great Basin Transmission, LLC's request for approval of an amended tariff filing and rate incentives for the SWIP-N transmission line. The protest comes amidst recent policy changes and environmental concerns that threaten the project's viability and environmental integrity. Stop Lava Ridge, Inc. argues that Great Basin's failure to show any new generation in Idaho, combined with the U.S. Department of Interior's recent policy changes, significantly reduce the potential for the SWIP-N transmission line to succeed.
Key Takeaways:
- Stop Lava Ridge, Inc. has filed a motion to protest the Great Basin Transmission, LLC's request for approval of an amended tariff filing and rate incentives for the SWIP-N transmission line.
- The protest is based on the company's failure to show any new generation in Idaho and the U.S. Department of Interior's recent policy changes that significantly reduce the potential for the SWIP-N transmission line to succeed.
- The policy changes include Secretary's Order #3438, which imposes a new "capacity density" requirement on renewable energy projects on federal land, and a DOI Memorandum that steps up enforcement of the Bald and Golden Eagle Protection Act.
- The policy changes and enforcement actions will further limit the development of wind and solar projects on federal lands in Idaho, Nevada, and other Western States.
- Stop Lava Ridge, Inc. encourages the Commission to deny the requested rate incentives based on Great Basin's failure to show any new generation in Idaho and its failure to take all reasonable steps to mitigate risk.
- The Jerome County Board of Commissioners has scheduled a hearing on September 22, 2025 to consider an appeal of a Jerome County Planning and Zoning Commission decision that would issue special use permits to construct SWIP-N transmission towers.
- Stop Lava Ridge, Inc. is a coalition of farmers, ranchers, and community members dedicated to protecting the Magic Valley from Magic Valley Energy's Lava Ridge wind project, Great Basin Transmission's proposed SWIP-N transmission line, and other federal wind projects proposed for Southern Idaho.
- The Lava Ridge wind project has been terminated due to President Trump's Day One Presidential Memorandum, and Magic Valley Energy has withdrawn its right-of-way authorization.
Statistics:
- 116.5 MW of north-to-south transmission is needed to support debt and equity financing in Great Basin's amended application.
- 1,000 MW of Idaho wind energy is required to support California's goal of accessing 1,000 MW of wind energy from Idaho.
- 33.17 megawatts (MW) per acre is the energy generation capacity of one advanced nuclear plant.
- 0.006 MW/acre is the energy generation capacity of one offshore wind farm, which is approximately 5,500 times less efficient than one nuclear plant.
Sources:
- Fox News, "Idaho farmer blasts Biden over windmill project: It'll 'destroy the desert,' ship energy to California: Dean Dimond says landowners are being offered 'pennies' on the dollar," January 6, 2023.
- Politico, "Another Burgum order coldcocks solar and wind: The Friday order by the Interior secretary on the "capacity density" of solar and wind projects is the latest in a series of restrictive moves by the Trump administration," dated August 4, 2025.
- U.S. Fish and Wildlife Service, "Bald and Golden Eagle Protection Act."
- U.S. Department of the Interior, "Interior Department Moves to Cancel Reckless Biden-era Approval of Lava Ridge Wind Project," press release dated August 6, 2025.
- U.S. Department of the Interior, "Secretary Burgum Announces Order to Rein In Environmentally Damaging Wind and Solar Projects," dated August 1, 2025.
- U.S. Department of the Interior, "Decision-Right-of-way Grant-IDID105841803," dated August 5, 2025.
- Heatmap News, "Interior Department Targets Wind Developers Using Bird Protection Law: A new letter sent Friday asks for reams of documentation on developers' compliance with the Bald and Golden Eagle Protection Act," dated August 11, 2025.
- Energywire, "Interior demands eagle data from wind developers: Supporters of renewable energy say the Trump administration could use the records to take action against wind energy projects," dated August 12, 2025.