Texas Eastern Transmission, LP is undertaking a project to replace and offset three existing pipeline segments at a crossing of Cove Mountain Road in Blair County, Pennsylvania. The project involves installing new 24-inch diameter Line 12 pipeline, 30-inch diameter Line 19 pipeline, and 30-inch diameter Line 27 pipeline. The replacement is necessary due to changes in pipeline class locations resulting from development and encroachment along the company's right-of-way to ensure public safety and maintain compliance with the Department of Transportation's Minimum Federal Safety Standards.

The project has made significant progress, with 100% completion of site prep activities, topsoil stripping, and erosion/sedimentation control installation. The team has also completed final tie-ins, welding, and replaced piping removal. However, demobilization and site restoration/final clean-up activities are still ongoing, with 67% and 89% completion, respectively.

Key Takeaways:

  • The project involves the replacement and offsetting of three existing pipeline segments, spanning a total of 5,476 feet of new 24-inch diameter Line 12 pipeline, 5,436 feet of new 30-inch diameter Line 19 pipeline, and 434 feet of new 30-inch diameter Line 27 pipeline.
  • The replacement is necessary due to changes in pipeline class locations resulting from development and encroachment along the company's right-of-way to ensure public safety and maintain compliance with the Department of Transportation's Minimum Federal Safety Standards.
  • The project has made significant progress, with 100% completion of site prep activities, topsoil stripping, and erosion/sedimentation control installation.
  • Demobilization and site restoration/final clean-up activities are still ongoing, with 67% and 89% completion, respectively.
  • The team has also completed final tie-ins, welding, and replaced piping removal.
  • Restoration and revegetation monitoring will continue in the upcoming reporting period.

Statistics:

  • Total length of new pipeline to be installed: 5,476 feet (Line 12) + 5,436 feet (Line 19) + 434 feet (Line 27) = 11,346 feet
  • Total number of pipeline segments to be replaced: 3
  • Percentage of site prep activities completed: 100%
  • Percentage of topsoil stripping completed: 100%
  • Percentage of erosion/sedimentation control installation completed: 100%
  • Percentage of demobilization completed: 67%
  • Percentage of site restoration/final clean-up completed: 89%