The Federal Energy Regulatory Commission has received an updated document from Texas Gas Transmission, LLC regarding the Kosciusko Junction Pipeline Project. The document, submitted on October 13, 2025, includes two attachments: an updated list of addresses for affected landowners and an updated list of addresses for stakeholders. The applicants, Gulf South Pipeline Company, LLC and Texas Gas Transmission, LLC, note that the updated landowner list corrects and adds several addresses, including those marked in red font and those that were returned as "undeliverable." The applicants request that the affected landowner list be treated as Privileged Information, citing potential risks to the assets and personnel of the applicants.
Key Takeaways:
- The updated landowner list includes corrections and additions, with several addresses marked in red font and others returned as "undeliverable."
- The applicants request that the affected landowner list be treated as Privileged Information, citing potential risks to the assets and personnel of the applicants.
- The applicants have mailed notices to all affected landowners, towns, communities, and local, state, and federal governments and agencies affected by the Project.
- The pipeline systems are a vital component of the United States' energy infrastructure, providing natural gas transportation and related services to various customers.
- The applicants have submitted the updated lists to the Commission on October 13, 2025, and have requested that the affected landowner list be treated as Privileged Information.
- The Director of Regulatory Affairs, Juan Eligio, Jr., has submitted the document to the Commission and is available for questions at (713) 479-3480.
Statistics:
- The document was submitted to the Federal Energy Regulatory Commission on October 13, 2025.
- The applicants mailed notices to all affected landowners, towns, communities, and local, state and federal governments and agencies affected by the Project on September 30, 2025.
- The updated landowner list includes several corrections/additions noted in red font, as well as addresses that were returned as "undeliverable."
- The pipeline systems provide natural gas transportation and related services to a variety of customers.
Sources:
- Texas Gas Transmission, LLC. (2025, October 13). Updated Landowner and Stakeholder Lists for the Kosciusko Junction Pipeline Project. Federal Energy Regulatory Commission.
- 18 C.F.R. § 388.112 - Privileged Information.
- 18 C.F.R. § 157.6(d)(5) - Abbreviated Applications.