Uncertainty Surrounds Baku to Ceyhan Pipeline Development
Azerbaijan's western oil companies continue to wait for Turkey's specific terms and tariffs for the Baku to Ceyhan pipeline, despite Ankara's assertions that details have been disclosed. The pipeline, supported by Turkey and the US for economic and strategic reasons, faces doubts about the availability of sufficient oil volumes to justify the estimated $3.7 billion construction cost. Washington has urged Turkey, Georgia, and Azerbaijan to partner with the Azerbaijan International Operating Company (AIOC) to reduce costs and ensure the project's commercial viability. Senior officials from Socar, the Azeri state oil company, the AIOC, and Turkey met in Ankara to discuss the necessary agreements between the proposed transit countries.
Key Takeaways:
- Azerbaijan International Operating Company (AIOC) estimates the construction cost of the 2,000km Baku to Ceyhan pipeline at $3.7 billion.
- Western oil companies doubt the availability of sufficient oil volumes to justify the construction cost.
- US views the Baku-Ceyhan pipeline as crucial to the region's political independence.
- Washington urges Turkey, Georgia, and Azerbaijan to partner with AIOC to reduce costs and ensure the project's commercial viability.
- Turkish officials expect Azerbaijan to complete the formation of the Main Export Pipeline Company by summer, when various host government and inter-governmental agreements can be ratified.
- Azerbaijan plans to invite AIOC members and other oil companies to take stakes in the Main Export Pipeline Company.
- Mapna, an Iranian project management company, has won a $347m deal to build a Caspian Sea oil pipeline to Iran's northern refineries.
Statistics:
- Estimated construction cost of the Baku to Ceyhan pipeline: $3.7 billion
- Length of the Baku to Ceyhan pipeline: 2,000km
- Estimated timeline for completion of the Main Export Pipeline Company formation: summer
- Amount of deal won by Mapna for building a Caspian Sea oil pipeline: $347m
Sources:
- Reuters: "Turkey expects Azerbaijan to complete Main Export Pipeline Company by summer"
- Azerbaijan International Operating Company (AIOC): estimated construction cost of the Baku to Ceyhan pipeline
- Washington: urging Turkey, Georgia, and Azerbaijan to partner with AIOC to reduce costs and ensure the project's commercial viability
- National Iranian Oil Company (NIOC): awarding Mapna the deal for building a Caspian Sea oil pipeline
- Mapna: winning a $347m deal for building a Caspian Sea oil pipeline