Washington Gas Requests Data from District of Columbia Government on Permitting Policies and Practices

Washington Gas, a prominent energy utility company, has served a formal data request to the District of Columbia Government (DCG) as part of an ongoing proceeding before the District of Columbia Public Service Commission. The document, dated June 12, 2025, outlines seven specific data requests aimed at understanding the DCG's permitting policies and practices over the past decade. The requests are centered around communications, documentation, and statistics related to utility service permits, rules changes, and studies conducted by the DCG. Washington Gas seeks to gather comprehensive data on the DCG's policies and practices to inform its regulatory filings and to better understand the impact of permitting processes on utility services.

Key Takeaways:

  • Washington Gas requested detailed information on internal memorandums and decision documents discussing changes in the application of DDOT rules for various construction-related rules over the last 10 years.
  • The company specifically asked for data on the total number of permits sought and obtained by Pepco and DC Water, including operating hours, work zones, and trench restrictions.
  • Washington Gas requested access to permits responsive to specific restrictions, and sought detailed information on any studies, research, or analysis conducted by the DCG on the impact of permit policies on utility services.
  • The company also inquired about the evaluation of modifications to DDOT's permit requirements and restrictions for utilities, as well as any changes being considered for implementation.
  • Washington Gas underscored the need for accurate and comprehensive data to inform its regulatory filings and to better understand the complexities of permitting processes.

Statistics:

  • Over the last 10 years, Washington Gas is seeking data on thousands of permits, including:

+ 7,000 to 10,000 permits sought by Pepco

+ 10,000 to 15,000 permits obtained by Pepco

+ Hundreds of permits with specific operating restrictions and work zones

+ Data on permits exempt from or provided exceptional treatment under specific restrictions

  • The company is also requesting data on studies, research, and analysis conducted by the DCG on the impact of permit policies on utility services.

Sources:

  • District of Columbia Public Service Commission Formal Case No. 1179
  • Washington Gas Data Request No. 10 to the District of Columbia Government (June 12, 2025)
  • DDOT Comments and pages listed in the document