Wisconsin Public Service Commission Reviews American Transmission Company's Central Wisconsin Transmission Line Project

The Public Service Commission of Wisconsin has provided an update on its review of the American Transmission Company LLC (ATC) and Northern States Power Company-Wisconsin (NSPW) application for the Grid Forward - Central Wisconsin Transmission Line Project. The proposed project, part of the Midcontinent Independent System Operator's (MISO) Long Range Transmission Planning (LRTP) Tranche 1, aims to integrate more low-cost renewable resources into the transmission system, reduce congestion, and produce fuel cost savings. The project involves the construction of a new 345 kilovolt (kV) high voltage transmission line connecting the Tremval Substation to the Arpin Substation and terminating at the Columbia Substation.

Key Takeaways:

  • The proposed project is part of MISO's LRTP Tranche 1, aiming to reduce congestion and produce fuel cost savings by integrating more low-cost renewable resources.
  • The project involves the construction of a new 345 kV high voltage transmission line, approximately 200 miles long, with estimated costs between $1.596 billion and $1.630 billion.
  • The proposed project will use self-supporting tubular steel monopole structures with several structure types and configurations, accommodating different angles, dead-end structures, and terrain.
  • Commission staff reviewed the applicants' PowerWorld modeling analysis, verifying the results and concluding that the proposed project will improve reliability and resiliency of the regional transmission system.
  • The project includes the expansion of the Arpin Substation for a new 345 kV yard, the addition of an additional 345 kV position at the Columbia Substation, and modifications at several other substations.
  • The proposed project will have a total contingency reserve representing approximately 15 percent of the cost estimate.

Statistics:

  • Estimated project cost: $1.596 billion - $1.630 billion
  • Length of the proposed transmission line: approximately 200 miles
  • PowerWorld modeling analysis: verified and concluded that the proposed project will improve reliability and resiliency
  • Number of substations to be modified: several
  • Total contingency reserve: approximately 15% of the cost estimate

Sources:

  • [Public Service Commission of Wisconsin Direct Testimony of Bert Chee, Division of Energy Regulation and Analysis, American Transmission Company LLC, and Northern States Power Company-Wisconsin, Docket 5-CE-157, July 10, 2025]
  • [https://apps.psc.wi.gov/]