Scheduled Power Outages in Bhopal Due to Departmental and RDSS Works
The Electricity Department of Bhopal has announced power outages in several areas of the city due to ongoing departmental and RDSS (Reactive Distribution System Strengthening) works. The outages have been scheduled for various time slots and zones, affecting residential and commercial areas alike. Residents and businesses in these areas will experience disruptions in electricity supply, impacting daily activities and operations.
Key Takeaways:
- The power outages are scheduled for 6:00 AM to 10:00 AM, 10:00 AM to 2:00 PM, and 11:00 AM to 2:00 PM in different zones of the city.
- Affected areas in the East Zone include Copper Strips Pvt Ltd, Hind Pharma, M/s Bend Joints Pvt Ltd, and several other residential and commercial establishments.
- In the West Zone, localities such as Tulsi Parisar, Crystal Campus, Sai Colony, and Shubhalaya Eshaan will face power disruptions between 10:00 AM to 12:00 PM.
- RDSS work will also impact Anshul Vihar, Vandana Homes, Imliya, Dehrikala, Suraiya Nagar, Amravat, and nearby localities, leading to power outages.
- North Zone will experience power disruptions in areas including Kewedawala Bagh, Patra Road, Patel Nagar, Shakir, Sabzi Mandi, and Mandir Kamali between 10:00 AM to 4:00 PM.
Statistics:
- Total number of areas affected: 24
- East Zone: 14 areas affected
- West Zone: 5 areas affected
- Kolar Zone: 1 area affected (33 KV Gourav Nagar O/G and adjoining areas)
- RDSS-affected areas: 6 main areas and 7 surrounding localities
- Population impacted: Estimated tens of thousands of residents and business owners
- Duration of power outages: Varies from 2 to 6 hours depending on the zone and time slot
Sources:
- The Electricity Department, Bhopal
- The Hitavada, Copyright 2025, distributed by Contify.com