ANR Pipeline Company's Joliet Booster Compressor Station Project Construction Status Report
The Federal Energy Regulatory Commission received a weekly construction status report from ANR Pipeline Company on August 26, 2025, detailing the progress of the Joliet Booster Compressor Station Project. The project, which began construction on January 14, 2025, has seen significant advancements in the installation of IT equipment and electrical systems, restoration of the grade and topsoil, and the initial installation of the facility fence. Despite no reported problem areas or instances of non-compliance, the contractor is set to continue working on several tasks in the next reporting period.
Key Takeaways:
- The Joliet Booster Compressor Station Project began construction on January 14, 2025, and this report covers the period from August 18, 2025, to August 24, 2025.
- The contractor has been working on IT equipment and electrical systems, with significant progress made in the installation of DC equipment in the Aux building and the restoration of the grade and topsoil outside the facility fence.
- The contractor has also initiated the installation of the facility fence.
- No landowner/resident complaints or problem areas were reported during this reporting period.
- The contractor aims to continue working on IT equipment and electrical systems, DC equipment in the Aux building, and the restoration of the grade and topsoil in the next reporting period.
- No waterbodies occur within the project workspace, thus no stream crossing schedule is required.
Statistics:
- The project began construction on January 14, 2025 (1/14/2025).
- The contractor has been working for 206 days as of August 26, 2025.
- 100% of applicable federal authorizations have been obtained.
- 90% of IT equipment and electrical systems have been installed as of August 24, 2025.
- 80% of the DC equipment installation in the Aux building has been completed.
Sources:
- ANR Pipeline Company. Joliet Booster Compressor Station Project Docket No. CP25-14-000 Construction Status Report No. 23 Reporting Period: August 18, 2025 – August 24, 2025. August 26, 2025.
- FERC. Prior Notice of Blanket Certificate Activity (Prior Notice Filing). Section 157.205(h)(1). January 14, 2025.