Columbia Gas Transmission, LLC D74 Booster Compressor Project Update
Columbia Gas Transmission, LLC has provided an update on the D74 Booster Compressor Project, a high-priority infrastructure development aimed at enhancing the safety and reliability of the nation's energy infrastructure. The update, submitted to the Federal Energy Regulatory Commission (FERC), highlights the project's current status and progress. As of June 22, 2025, the contractor has made significant strides in survey activities, equipment mobilization, and erosion control device installation. The report notes that no streams will be crossed during the project, and no landowner or resident complaints have been received. The update also includes photos of the construction work area, showcasing the progress made in protecting the environment.
Key Takeaways:
- The contractor has initiated survey activities, equipment mobilization, and erosion control device installation as part of the D74 Booster Compressor Project.
- All applicable federal authorizations have been obtained for the project.
- No streams will be crossed during the project, and no landowner or resident complaints have been received.
- The contractor has made significant progress in protecting the environment, as evident from the photos included in the update.
- The project's progress aligns with the scheduled timeline, with the contractor planning to install permanent construction entrance, continue topsoiling activities, and begin excavation and material transport in the next reporting period.
- The project's environmental plans and permit have been complied with, with no non-compliance issues observed at the time of inspection.
Statistics:
- The project's construction status report is submitted bi-weekly, with the most recent report dated June 24, 2025.
- The contractor has been active on the site since May 6, 2025, when they were authorized to commence construction activities.
- The project's priority is to enhance the safety and reliability of the nation's energy infrastructure.
Sources:
- Federal Energy Regulatory Commission (FERC) - [1]
- Columbia Gas Transmission, LLC - [2]
- 18 C.F.R. § 157.208(c)(10) - [3]
- Section 157.205(h)(1) of the Commission's regulations - [4]