Crusader Self-Propelled Howitzer Development Falls Behind Schedule
The Army's high-profile Crusader self-propelled howitzer is up to a year behind schedule, according to officials. The program has sought the help of another company, Honeywell, to sort out the issues. The proposed budget for fiscal 2000 is $348.7 million, but $75.8 million has been cut due to the delay. Despite the setback, appropriators have expressed support for the program, encouraging the Army to adequately fund it in future requests.
Key Takeaways:
- The Crusader self-propelled howitzer is the Army's No. 2 modernization priority behind the Comanche scout helicopter.
- The program is experiencing a software development delay, with completion now scheduled for February 2002.
- Prime contractor United Defense has asked Honeywell to join the program as a major player, with help from Honeywell not adding to the cost of software development.
- A single Crusader system, consisting of howitzer and resupply vehicle, costs $10.7 million.
- The current Army requirement is for 1,138 systems, although this number could drop if the Army moves to lighter divisions.
- The howitzer is the first armored vehicle to be fully digital from the ground up and the first with a fully automated loading and firing process.
- Honeywell's vast experience in aircraft avionics made it a good choice for Crusader, whose computer-display dominated cockpit looks more like part of a high-performance aircraft than a tracked vehicle.
- A Honeywell team is assessing the Crusader program, with results due by the end of the month.
- United Defense and Honeywell could sign a deal in 30 to 90 days.
- The system's increased capabilities make up for its extra weight, with Crusader weighing 55 tons.
- A crusader system consists of both vehicles, which can be flown on the Air Force's C-5 and C-17 airlifters.
- Defenders of Crusader admit its weight, but say its increased capabilities make it a better choice.
- Crusader would completely outclass Paladin, the system it will replace, according to the Army.
Statistics:
- 1.7 million: the number of lines of computer code in the Crusader program.
- 2,011: the new completion date for software development.
- $75.8 million: the amount cut from the proposed budget for fiscal 2000.
- $348.7 million: the proposed budget for fiscal 2000.
- $10.7 million: the cost of a single Crusader system.
- 1,138: the current Army requirement for Crusader systems.
- 20-25 years: the timeframe for the next generation of armored vehicles and fire-support weapons.
- 251 miles: the vehicle range of Crusader compared to Paladin's 186 miles.
- 41 mph: the speed of Crusader compared to Paladin's 34 mph.
- 12 mph: the speed of Crusader in reverse compared to Paladin's 7 mph.
- 60: the number of rounds Crusader can carry compared to Paladin's 27.
Sources:
- The fiscal 2000 defense-appropriations bill.
- United Defense executives.
- Army officials.
- General Eric Shinseki, Chief of Staff.
- Jim Unterseher, Crusader program director.
- Col Mike Cuff, artillery branch at Fort Sill, Okla.
- Col Charles Cartwright, Army program manager.
- Staff Sgt. Gerald Palmer, Paladin crewman.
- Staff Sgt. Eric Vann, Paladin crewman.