Eastern Gas Transmission and Storage Files Application for Appalachian Reliability Project
The Federal Energy Regulatory Commission has received an application from Eastern Gas Transmission and Storage, Inc. (EGTS) to build a pipeline and other facilities across parts of Pennsylvania and Ohio. The Appalachian Reliability Project aims to provide firm natural gas transportation service to a significant area, with an estimated daily capacity of 550,000 dekatherms. The project's construction and modifications are expected to cost over $238 million. EGTS has also filed a petition to waive a part of FERC's regulations, which will be reviewed by FERC staff within 90 days.
Key Takeaways:
- The Appalachian Reliability Project, proposed by Eastern Gas Transmission and Storage, Inc. (EGTS), involves the construction of 3.9 miles of 30-inch-diameter pipeline and the addition of compression at two existing compressor stations.
- The project aims to provide 550,000 dekatherms of firm natural gas transportation service per day, with an estimated cost of over $238 million.
- EGTS has filed a petition to waive a part of FERC's regulations, which will be reviewed by FERC staff within 90 days.
- The public has the opportunity to participate in the environmental review by filing comments or protests, with a deadline of August 28, 2025.
- Intervenors can challenge FERC orders in the U.S. Circuit Courts of Appeal.
- The Federal Energy Regulatory Commission's (FERC) Office of Public Participation is available to assist the public with inquiries and filings.
Statistics:
- 3.9 miles: The length of the 30-inch-diameter pipeline to be constructed as part of the Appalachian Reliability Project.
- 30 inches: The diameter of the pipeline to be constructed.
- 2: The number of existing compressor stations where compression will be added.
- 2: The number of meter regulation stations that will be modified.
- 550,000 dekatherms: The daily capacity of firm natural gas transportation service that the project aims to provide.
- $238 million: The estimated cost of the work associated with the Appalachian Reliability Project.
- 90 days: The timeframe for FERC staff to conduct the environmental review.
- August 28, 2025: The deadline for the public to file comments, protests, or motions to intervene.
- August 12, 2023: The day Eastern Gas Transmission and Storage, Inc. submitted the application to FERC.
- July 24, 2023: The day Eastern Gas Transmission and Storage, Inc. submitted the petition to waive a part of FERC's regulations.
Sources:
- Targeted News Service: "WASHINGTON, Aug. 12 (TNSFR) -- Eastern Gas Transmission and Storage, Inc. (EGTS) filed an application with the Federal Energy Regulatory Commission to build a pipeline and other facilities across parts of Pennsylvania and Ohio."
- Federal Register: "View Federal Register here: https://www.federalregister.gov/agencies/federal-energy-regulatory-commission"