Federal Energy Regulatory Commission Accepts Delegated Order for PJM Interconnection

The Federal Energy Regulatory Commission (FERC) has accepted a delegated order for PJM Interconnection, L.L.C., regarding the amended Interconnection Service Agreement and Interconnection Construction Service Agreement between Illinois Generation, LLC, Commonwealth Edison Company, and PJM. The agreements were submitted on April 30, 2025, and accepted for filing, effective June 30, 2025. The commission acknowledged no protests or adverse comments were filed, and granted motions to intervene out-of-time. This action does not constitute approval of any service or rate, and is without prejudice to any findings or orders that may be made in the future.

Key Takeaways:

  • The Federal Energy Regulatory Commission (FERC) issued a delegated order for PJM Interconnection, L.L.C. on June 25, 2025.
  • The order accepted the amended Interconnection Service Agreement and Interconnection Construction Service Agreement between Illinois Generation, LLC, Commonwealth Edison Company, and PJM.
  • The agreements were submitted on April 30, 2025, and accepted for filing, effective June 30, 2025.
  • No protests or adverse comments were filed, and motions to intervene out-of-time were granted.
  • This action does not constitute approval of any service or rate, and is without prejudice to any findings or orders that may be made in the future.
  • The order constitutes final agency action and requests for rehearing by the Commission may be filed within 30 days of the date of issuance.

Statistics:

  • Date of submission: April 30, 2025
  • Date of acceptance: June 25, 2025
  • Effective date: June 30, 2025
  • Number of agreements submitted: 2 (Interconnection Service Agreement and Interconnection Construction Service Agreement)
  • Number of parties involved: 3 (Illinois Generation, LLC, Commonwealth Edison Company, and PJM)

Sources:

  • FERC Order: ER25-2087-000 (issued on June 25, 2025)
  • PJM Interconnection, L.L.C. PJM Service Agreements Tariff (PJM SA No. 6829 and PJM SA No. 6830)
  • 18 C.F.R. § 375.307 (authority delegated to the Director, Division of Electric Power Regulation - East)
  • 18 C.F.R. § 385.713 (requests for rehearing)