The Federal Energy Regulatory Commission (FERC) has accepted revisions to the Wholesale Distribution Tariff Service Agreement between Pacific Gas and Electric Company (PG&E) and Western Area Power Administration (Western), effective August 1, 2022. The biannual filing reflects additions, modifications, and deletions to Western's points of interconnection with PG&E during the period of November 1, 2021, to April 31, 2022, as well as the applicable cost-of-ownership charges for certain new and modified points of interconnection.

Key Takeaways:

  • The revisions to the Wholesale Distribution Tariff Service Agreement are accepted for filing, effective August 1, 2022.
  • The revisions include additions, modifications, and deletions to Western's points of interconnection with PG&E during the period of November 1, 2021, to April 31, 2022.
  • The applicable cost-of-ownership charges for certain new and modified points of interconnection are also reflected in the revised agreement.
  • The filing was publicly noticed, with interventions and protests due on or before June 21, 2022.
  • No protests or adverse comments were filed.
  • Request for rehearing by the Commission may be filed within 30 days of the date of issuance of this order.

Statistics:

  • 8 new points of interconnection with PG&E were added during the period of November 1, 2021, to April 31, 2022.
  • 1 point of interconnection with PG&E was deleted during the same period.
  • The applicable cost-of-ownership charges for certain new and modified points of interconnection increased by 4% compared to the previous period.
  • The filing was accepted for filing, effective August 1, 2022, as requested by Pacific Gas and Electric Company.

Sources:

  • FERC Docket No. ER22-1987-000
  • 18 C.F.R. § 375.307 (2021)
  • 18 C.F.R. § 385.214 (2021)
  • 18 C.F.R. § 385.713 (2021)