Federal Energy Regulatory Commission Approves Dominion Energy South Carolina's Delegated Order

The Federal Energy Regulatory Commission (FERC) has issued a delegated order approving Dominion Energy South Carolina, Inc.'s (DESC) Engineering and Procurement Agreement between DESC Electric Transmission and DESC Power Generation. The approval was granted on July 31, 2025, following the submission of the agreement on June 3, 2025. The agreement, designated Service Agreement No. 250, aims to support the development of a new transmission line in the state. FERC's approval does not constitute a final determination on the agreement's approval, and the Commission reserves the right to make further findings or orders in any proceeding related to the agreement.

Key Takeaways:

  • The FERC approved Dominion Energy South Carolina's Engineering and Procurement Agreement between DESC Electric Transmission and DESC Power Generation on July 31, 2025.
  • The agreement, designated Service Agreement No. 250, was submitted on June 3, 2025, and aims to support the development of a new transmission line in the state.
  • The FERC's approval does not constitute a final determination on the agreement's approval, and the Commission reserves the right to make further findings or orders in any proceeding related to the agreement.
  • The agreement is part of the FERC's efforts to promote the development of new transmission lines and improve the reliability of the nation's transmission grid.
  • The FERC's approval is consistent with the provisions of 18 C.F.R. § 375.307, which authorizes the Director, Division of Electric Power Regulation - East, to delegate authority to accept filings for certain electric transmission and generation projects.
  • The FERC's decision does not affect any existing service rates, charges, or practices related to the agreement.

Statistics:

  • The FERC issued the delegated order on July 31, 2025 (Issued Date: referenced in the source material).
  • The agreement was submitted on June 3, 2025 (File Date: referenced in the source material).
  • The FERC reserves the right to make further findings or orders within 30 days of the date of issuance of this order (Reference: 18 C.F.R. § 385.713).

Sources:

  • Federal Energy Regulatory Commission, WASHINGTON, DC 20426, OFFICE OF ENERGY MARKET REGULATION, Dominion Energy South Carolina, Inc., Docket No. ER25-2411-000, Issued: July 31, 2025.