Federal Energy Regulatory Commission Approves Gazebo Solar Energy Project

The Federal Energy Regulatory Commission has issued a delegated order approving the Gazebo Solar Energy project, a proposed solar energy facility in Indiana, Michigan. On June 25, 2025, the Commission accepted the filing of a Generation Interconnection Agreement among PJM Interconnection, L.L.C. as the transmission provider, Gazebo Solar Energy LLC as the project developer, and AEP Indiana Michigan Transmission Company, Inc. as the transmission owner. The agreement was submitted by PJM on April 28, 2025, and was accepted effective March 28, 2025, as requested. The project has not received any protests or adverse comments, and the Commission has granted notices of intervention and motions to intervene.

Key Takeaways:

  • The Federal Energy Regulatory Commission has approved the Gazebo Solar Energy project, a proposed solar energy facility in Indiana, Michigan.
  • The project was developed by Gazebo Solar Energy LLC and involves a Generation Interconnection Agreement with PJM Interconnection, L.L.C. as the transmission provider, and AEP Indiana Michigan Transmission Company, Inc. as the transmission owner.
  • The agreement was submitted by PJM on April 28, 2025, and was accepted by the Commission on June 25, 2025.
  • The project has not received any protests or adverse comments, and the Commission has granted notices of intervention and motions to intervene.
  • The approval does not constitute an approval of any service, rate, charge, classification, or any rule, regulation, contract, or practice affecting the rate or service provided for in the filed document(s).
  • The Commission's approval is without prejudice to any findings or orders which have been or may hereafter be made by the Commission in any proceeding now pending or hereafter instituted by or against the applicant(s).
  • Requests for rehearing by the Commission may be filed within 30 days of the date of issuance of this order.

Statistics:

  • The Gazebo Solar Energy project was submitted by PJM on April 28, 2025.
  • The project was accepted by the Commission on June 25, 2025, effective March 28, 2025, as requested.
  • The Commission has granted notices of intervention and motions to intervene.
  • There were no protests or adverse comments filed in relation to the project.
  • The Commission's approval is without prejudice to any findings or orders which have been or may hereafter be made by the Commission in any proceeding now pending or hereafter instituted by or against the applicant(s).
  • Requests for rehearing by the Commission may be filed within 30 days of the date of issuance of this order.

Sources:

  • Federal Energy Regulatory Commission, "Delegated Order: FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, DC 20426 OFFICE OF ENERGY MARKET REGULATION PJM Interconnection, L.L.C. Docket No. ER25-2064-000 Issued: June 25, 2025"
  • PJM Interconnection, L.L.C., "PJM Service Agreements Tariff, PJM SA No. 7641, PJM SA No. 7641 among PJM, Gazebo Solar and IMTCo (0.0.0)."
  • 18 C.F.R. § 35.3(a)(2).